What are thresholds in P6?
A threshold is a user-defined trigger that identifies when the status of an activity has exeeded or is close to moving beyond an acceptable range.
Thresholds are created by:
- Selecting a parameter ex. start date variance, cost variance, cost % of budget
- Set lower and upper values for the threshold’s range
- Apply the threshold to a specific work breakdown structure
- You can monitor the threshold at the activity level.
- You can monitor the threshold at the WBS level.
The difference between the two ways of monitoring is how Primavera P6 EPPM groups issues. If you monitor a threshold at the activity level, then issues are created for each activity that violates the threshold’s range. If you monitor thresholds at the WBS level, then the activities’ issues will be summarized and reported at the WBS element, rather than each activity.
Once you have defined a threshold in P6, it can be monitored to identify whether it has any issues associated with it.
For example: Set up a threshold using the Total Float parameter.
- the lower threshold value is 1D
- the upper threshold value is 10D
This video tutorial was posted on our Youtube channel awhile ago, but we thought it was valuable enough to post again. It covers utilizing thresholds in P6.
Visit our Project Management training section for our upcoming basic and advanced project management classes for P6. Cant make a training class? That’s okay! We also offer self-paced online video training course for basic and advanced project management techniques or visit to our free tutorial section.